The
committee shall:
(1) Certify, or recertify, public bodies for a period of
three years to use the design-build or general
contractor/construction manager, or both, contracting procedures
for projects with a total project cost of ten million dollars or
more;
(2) Review and approve the use of the design-build or
general contractor/construction manager contracting procedures on
a project by project basis for public bodies that are not
certified under RCW 39.10.270; and
(3) Review and approve the use of the general
contractor/construction manager contracting procedure by
certified public bodies for projects with a total project cost
under ten million dollars.
[2007 c 494 § 105.]
NOTES:
Sunset Act application: See note following chapter digest.