If charged with a violation of RCW 19.122.090, an
operator will be deemed to have established an affirmative
defense to such charges if:
(1) The operator was provided a valid excavation
confirmation code;
(2) The excavation was performed in an emergency situation;
(3) The operator was provided a false confirmation code by
an identifiable third party; or
(4) Notice of the excavation was not required under this
chapter.
[2005 c 448 § 6.]