Scope of Work Format
Attachment A: Scope of Work
City of Yakima
Contract # (to be provided by CTED)
Project Title: 2002 GMA Update
The GRANTEE is responsible for the preparation of all contract deliverables set forth below. The process and product shall be substantially consistent with the GRANTEE's grant application submitted to the Department for this round of funding and with the requirements of the Growth Management Act. Deliverables will be provided to the Department in electronic format wherever possible. At the Department's or the GRANTEE's request, deliverables may be provided in paper format.
Project Description:
· Review our Critical Areas Ordinance to see if it incorporate the best available science and consideration for anadromous fisheries as required by RCW 36.70A.172.
· Capital Facilities Plan update.
· Transportation Plan update.
· Population projections as it relates to the urban growth area.
· Time permitting, citizen requests for amendments to the Future Land Use Map.
Milestones:
A tentative Comp Plan amendment schedule as follows:
Nov. 01 - Jan. 02: Review plan, research, attend workshops
Feb./March: Regional Planning Commission workshops
April: Regional Planning Commission meetings on Population
May: Regional Planning Commission meetings on Critical Areas
June: Regional Planning Commission meetings on Transportation
July: Regional Planning Commission public hearings
August: City Council public hearing
September: City Council adopts Comprehensive Plan Amendments
Deliverables: Adopt comprehensive plan amendments, and/or an adopted resolution indicating the Grantee's completion or progress and intent in meeting the GMA update requirement in September 2002.
Resources: budget for update as in the grant application.
Contracts $25,000
Goods & Services: $23,000
Travel/Training: $2,000